Vancouver, BC, Canada – First Majestic Silver Corp. (NYSE:AG) (TSX:FR) (FSE:FMV) (the “Company” or “First Majestic”) announces that total production in the fourth quarter of 2023 from the Company’s three producing mines in Mexico, namely the San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver Mine reached 6.6 million silver equivalent (“AgEq”) ounces, consisting of 2.6 million silver ounces and 46,585 gold ounces. Total production for the full year of 2023 consisted of 26.9 million AgEq ounces, aligned to the Company’s 2023 revised guidance of between 26.2 to 27.8 million AgEq ounces, consisting of 10.3 million silver ounces and 198,921 gold ounces.

Q4 2023 HIGHLIGHTS

  • Total Production Increased by 6% Q/Q:  Total production reached 6.6 million AgEq ounces in Q4, representing a 6% increase when compared to 6.3 million AgEq ounces produced in the previous quarter. The higher production is related to record quarterly production at Santa Elena of 3.0 million AgEq ounces, partially offset by lower silver production at La Encantada due to the ongoing limited water availability.
  • Record production at Santa Elena – up 13% Q/Q:  Santa Elena achieved a new quarterly production record in Q4. Strong metal recoveries and grades from Ermitaño enabled Santa Elena to produce 3.0 million AgEq ounces in the fourth quarter, representing a 13% increase compared to the prior quarter.
  • Safety:  The 2023 consolidated Total Reportable Incident Frequency Rate (“TRIFR”) was 1.02 and the Lost Time Incident Frequency Rate (“LTIFR”) was 0.34, an improvement of 16% and 33% compared to prior year, respectively.
  • Environmental, Social and Governance (“ESG”):  First Majestic’s ESG score with Sustainalytics has improved from 50.56 in 2022 to 31.0 by the end of 2023, putting the Company in the top 38% of its industry peers.
  • 16 Active Drill Rigs:  The Company completed a total of 32,881 metres (“m”) of drilling across its mines in Mexico during the fourth quarter. Throughout the quarter, up to sixteen drill rigs were active consisting of twelve rigs at San Dimas, and four rigs at Santa Elena.

FY 2023 HIGHLIGHTS

  • Consolidated production in 2023 reached 26.9 million AgEq ounces, aligned to the midpoint of the 2023 revised guidance of between 26.2 to 27.8 million AgEq ounces. The-year-over-year decrease can be attributable to the temporary suspension of Jerritt Canyon that was announced by the Company on March 20, 2023.
  • Silver production reached 10.3 million ounces, compared to revised guidance range of between 10.5 to 11.2 million ounces, primarily due to lower silver production in H2 at La Encantada. Gold production in 2023 totaled 198,921 ounces aligned to the higher end of the Company’s revised guidance range of between 190,000 to 201,000 ounces.
  • Santa Elena produced a new annual record of 9.6 million AgEq ounces in 2023, representing a 5% increase compared to 2022. Mine output and grades from Ermitaño remained strong throughout 2023, and combined with record metallurgical recoveries facilitated by the newly commissioned dual-circuit plant, this enabled Santa Elena to deliver strong production in 2023.
  • The Company announced the launch of its 100%-owned and operated minting facility, First Mint, LLC (“First Mint”), which is currently in the commissioning stage. This facility will expand upon existing bullion sales through vertically integrating production of investment-grade fine silver bullion. This will allow First Majestic to sell a substantially greater portion of its silver production directly to its customers.
  • Completed the move of the ISO 9001:2015 certified Central Laboratory from Durango to Santa Elena.
  • Successfully closed the sales of the La Guitarra Silver Mine and the La Parrilla Silver Mine to Sierra Madre Gold & Silver Ltd. and Silver Storm Mining Ltd., respectively.

“First Majestic finished 2023 on a strong and positive note, despite the challenges endured earlier in the year, and I would like to congratulate the team on their hard work and efforts,” said Keith Neumeyer, the Company’s President & CEO. “Santa Elena had a stellar year with production reaching a record 9.6 million AgEq ounces while maintaining high safety standards. We are enjoying the dividends from the investments we made at Santa Elena over the last few years, and we are thrilled with these achievements. Earlier in the year, we made the difficult decision to temporarily suspend operations at Jerritt Canyon in Q1 while we focus on developing a new mine plan that is economic and sustainable for the operation including the investment in never drilled greenfield exploration targets at Jerritt Canyon. I’m also happy to announce our expanded exploration program for 2024. First Majestic is blessed with an enormous under-explored large land package surrounding three of the most important silver mines in Mexico as well as Jerritt Canyon in northern Nevada. We’re expecting 2024 to be an exciting year for our exploration team.”

Production Details Table:

Q4Q3Q/Q FYFYY/Y
20232023ChangeConsolidated Production Results20232022Change
652,731670,203(3%)Ore processed/tonnes milled2,901,9723,468,987(16%)
6,640,5506,285,7906%Total production – Silver equivalent ounces26,874,41731,252,920(14%)
2,612,4162,461,8686%Silver ounces produced10,250,75510,522,051(3%)
46,58546,7200%Gold ounces produced198,921248,394(20%)

Q4 2023 Mine-by-Mine Production Table:

MineOre ProcessedTonnes per DayAg Grade (g/t)Au Grade (g/t)Ag RecoveryAu RecoveryAg Oz ProducedAu Oz ProducedAgEq Oz Produced
San Dimas215,2322,3392342.7793%96%1,513,79118,4683,110,677
Santa Elena233,6012,5391063.8873%96%582,48428,0563,008,449
La Encantada203,8982,2161100.0171%90%516,14161521,424

– Certain amounts shown may not add exactly to the total amount due to rounding differences.
– The Ag:Au ratio used in the calculation of silver equivalent ounces was 86.5:1

San Dimas Silver/Gold Mine:

  • San Dimas produced 3,110,677 AgEq ounces during the quarter consisting of 1,513,791 ounces of silver and 18,468 ounces of gold, representing a 2% decrease and a 3% increase, respectively, when compared to the prior quarter.
  • The mill processed a total of 215,232 tonnes of ore with average silver and gold grades of 234 g/t and 2.77 g/t, respectively.
  • Silver and gold recoveries during the quarter averaged 93% and 96%, respectively.
  • The Central Block and Sinaloa Graben areas contributed approximately 78% and 22%, respectively, of the total production during the quarter.
  • During the quarter, a total of twelve drill rigs consisting of two surface rigs and ten underground rigs, completed 24,932 m of drilling on the property.

Santa Elena Silver/Gold Mine:

  • Santa Elena produced 3,008,449 AgEq ounces, a quarterly production record, consisting of 582,484 ounces of silver and 28,056 ounces of gold, representing a 67% increase in silver ounces and a 1% decrease in gold ounces when compared to the prior quarter. The increase in silver equivalent production was driven by higher silver grades and recoveries in the period.
  • The mill processed a total of 233,601 tonnes of ore, containing average silver and gold head grades of 106 g/t and 3.88 g/t, respectively.
  • Consolidated silver and gold recoveries averaged a record 73% and 96%, respectively, during the quarter. The strong metallurgical recoveries are due to the continuous operational optimization of the new dual-circuit plant.
  • During the quarter, four drill rigs consisting of two surface rigs and two underground rigs, completed 7,949 m of drilling on the property.

La Encantada Silver Mine:

  • Throughout H2 2023, La Encantada was impacted by limited water supply to the mill, mainly driven by severe drought conditions in 2023 which impacted the existing water wells in the area. During Q3 and Q4 2023, management drilled a total of three exploration and production holes in an effort to source additional water. To date, these efforts have had limited success. The Company has identified several new targets that will be drilled in Q1 and Q2 2024 to identify additional water sources and allow for the mill to process ore tonnes at budgeted rates.
  • During the quarter, La Encantada produced 516,141 ounces of silver, representing a 9% decrease compared to the prior quarter.
  • The mill processed a total of 203,898 tonnes of ore with an average silver grade and recovery of 110 g/t and 71%, respectively. Stope production from the new Beca Zone has contributed 48,811 tonnes with average silver grades of 121 g/t.
  • Looking forward to 2024, management has decided to take a conservative approach when it comes to our guidance on production and costs at La Encantada. Despite the fact management believes a water source will be discovered, thereby restoring La Encantada to its historical production numbers and costs, the timing for the discovery of this positive outcome is currently not known.  

2024 PRODUCTION GUIDANCE

The Company expects to achieve total production in 2024 from its three operating mines in Mexico of between 21.1 to 23.5 million AgEq ounces consisting of 8.6 to 9.6 million ounces of silver and 150,000 to 167,000 ounces of gold. The decrease in forecasted gold production is primarily due to the temporary suspension of the Jerritt Canyon Gold Mine in Nevada announced in Q1 2023.

A mine-by-mine breakdown of the 2024 production guidance is included in the table below. The Company reports cost guidance to reflect cash costs and AISC on a per AgEq payable ounce. For 2024, the Company is using an 83:1 silver to gold ratio, consistent with its revised 2023 guidance. Metal price and foreign currency assumptions for calculating equivalents are silver: $24.00/oz, gold: $2,000/oz, MXN:USD 18:1.

GUIDANCE FOR 2024

 Silver Oz (M)Gold Oz (k)Silver Eqv Oz (M)Cash CostAISC
Operation:   ($ per AgEq oz)($ per AgEq oz)
San Dimas, Mexico5.3 – 5.969 – 7711.1 – 12.311.89 – 12.5715.54 – 16.57
Santa Elena, Mexico1.1 – 1.281 – 907.8 – 8.713.38 – 14.1016.25 – 17.26
La Encantada, Mexico2.2 – 2.42.2 – 2.424.03 – 24.5128.25 – 30.09
Operations Total:8.6 – 9.6150 – 16721.1 – 23.513.69 – 14.4618.62 – 19.90
      
Corporate:   ($ per AgEq oz)($ per AgEq oz)
General, Administration & Services0.70 — 0.78
Total:   ($ per AgEq oz)($ per AgEq oz)
Consolidated:8.6 – 9.6150 – 16721.1 – 23.513.69 – 14.4619.32 – 20.68

* Certain amounts shown may not add exactly to the total amount due to rounding differences.
* Cash Costs and AISC are non-GAAP measures and are not standardized financial measures under the Company’s financial reporting framework. The Company calculates cash costs and consolidated AISC in the manner set out in the table below. These measures have been calculated on a basis consistent with historical periods (see “Non-GAAP Financial Measures” below).

La Encantada’s 2024 production guidance has been adjusted lower to reflect a conservative view regarding the temporary limited water availability at La Encantada. We assume in this guidance that the water availability will remain an issue for all of 2024. The 2024 budget includes capital consideration to explore for additional water source in the area. Management is reviewing cost reduction programs at La Encantada to offset the low production impact on cost and remains optimistic that the water flow to the mill will return to historic levels within the year.

The Company is projecting its global 2024 AISC to be within a range of $19.32 to $20.68 on a per consolidated payable AgEq ounce basis. Excluding non-cash items, the Company anticipates its 2024 AISC to be within a range of $18.62 to $19.89 per payable AgEq ounce. An itemized AISC cost table is provided below:

All-In Sustaining Cost CalculationFY 2024 ($ /AgEq oz)
Total Cash Costs per Payable Silver Equivalent Ounce13.69   14.46
General and Administrative Costs1.55   1.72
Sustaining Development Costs1.14   1.21
Sustaining Property, Plant and Equipment Costs0.77 – 0.86
Profit Sharing0.82  – 0.91
Lease Payments0.65   0.73
Share-based Payments (non-cash)0.54  – 0.61
Accretion of Reclamation Costs (non-cash)0.16  – 0.18
All-In Sustaining Costs: (AgEq Oz)19.32  – 20.68
All-In Sustaining Costs: (AgEq Oz excluding non-cash items)18.62  – 19.89
  1. AISC is a non-GAAP measure and is calculated based on the Company’s consolidated operating performance. Other mining companies may calculate AISC differently as a result of differences in underlying accounting principles, the definition of “sustaining costs” and the distinction between sustaining and expansionary capital costs.
  2. Consolidated AISC includes general and administrative cost estimates and non-cash costs of $2.25 to $2.51 per AgEq ounce.
  3. For further details of these measures, including equivalent historical information, please see “Non-GAAP Measures” on pages 36-45 of the Company’s Management’s Discussion and Analysis for the third quarter of 2023, available on SEDAR+ at www.sedarplus.com and on EDGAR at www.sec.gov.

CAPITAL INVESTMENTS IN 2024

In 2024, the Company plans to invest a total of $125.0 million on capital expenditures consisting of $45.0 million for sustaining activities and $80.0 million for expansionary projects. This represents an 11% decrease compared to the 2023 revised capital expenditures and is aligned with the Company’s future growth strategy of increasing exploration and development activities at Santa Elena, San Dimas and Jerritt Canyon.

2024 Capital Guidance ($millions)SustainingExpansionaryTotal
Underground Development27.039.066.0
Exploration0.035.135.1
Property, Plant and Equipment17.64.321.9
Corporate Projects0.41.62.0
Total45.080.0125.0

The 2024 annual guidance includes total capital investments of $66.0 million for underground development; $21.9 million towards property, plant and equipment; $35.1 million in exploration; and $2.0 million towards corporate innovation projects. Management may revise the guidance during the year to reflect actual and anticipated changes in metal prices or to the business.

The Company plans to complete approximately 30,900m of underground development in 2024 compared to 34,046m completed in 2023. The 2024 development program consists of approximately 17,100m at San Dimas; 10,300m at Santa Elena and 3,500m at La Encantada. At San Dimas, the Company is planning to concentrate development metres in the Perez, Roberta, Regina and Elia Veins. At the Santa Elena district, underground development is expected to focus on Ermitaño. At La Encantada, the Company plans to develop the second levels of both the Ojuelas and Milagros orebodies for 2024 production.

The Company is planning approximately 188,500m of exploration drilling in 2024; this represents a significant increase compared to the 143,465m completed in 2023. The 2024 drilling program is expected to consist of:

  • At San Dimas, approximately 95,000m of drilling are planned with infill, step-out and exploratory holes focused on near mine and brownfield targets including major ore controlling structures in the West, Central and Sinaloa blocks. Exploration efforts represent a balanced approach to adding Inferred Resources along known veins, converting Inferred to Indicated Resources and identifying new veins in locations where post mineral cover has deferred work to date.
  • At Santa Elena, approximately 59,000m of drilling are planned. Greenfield and brownfield drilling at Santa Elena will focus on several targets within a 5-kilometre radius around the processing plant where the goal is to find a new mineralized vein. The Company is also planning to return to the Los Hernandez property, to test updated targets and projections of mineralized structures. Resource addition and conversion drilling is also to take place.
  • At Jerritt Canyon, approximately 25,000m of drilling are planned. Exploration work will be focused on drilling open ends of inferred mineralization with large volume potential as well as testing projections of ore controlling structures below outcropping Upper Plate (cover rock) where the presence of large, mineralized volumes is possible and has been poorly tested to date.
  • Finally, at La Encantada the Company has planned approximately 9,500m to continue searching for a new mineralized breccia body as well as to extend and de-risk some of the known veins and vein systems.

Q4 2023 EARNINGS AND DIVIDEND ANNOUNCEMENT

The Company is planning to release its fourth quarter 2023 audited financial results, and to announce the fourth quarter dividend payment and shareholder record and payable dates for the dividend payment on February 22, 2024.

CONFERENCE CALL DETAILS

The Company will host a conference call and webcast on Tuesday, January 16, 2024, at 8:00 a.m. (PT) / 11:00 a.m. (ET) to provide investors and analysts with a business update and to discuss its production results and 2024 guidance.

To participate in the conference call, please use the following dial-in numbers:

Canada & USA Toll-Free:1-800-319-4610
Outside of Canada & USA:+1-604-638-5340
Toll-Free Germany:0800 180 1954
Toll-Free UK:0808 101 2791

Participants should dial in at least 10 minutes prior to the call start to ensure placement into the conference on time.

A live webcast of the conference call will be accessible at the following link: https://services.choruscall.ca/links/fm2023q4.html

A webcast archive will be available approximately one hour after the end of the event and will be accessible for three months through the same link as the live event.

A recording of the conference call will be available for telephone replay approximately one hour after the end of the event by calling:

Canada & USA Toll-Free:1-800-319-6413
Outside of Canada & USA:+1-604-638-9010
Access Code:0637 followed by the # sign

The telephone replay will be available for seven days following the end of the event.

ABOUT THE COMPANY

First Majestic is a publicly traded mining company focused on silver and gold production in Mexico and the United States. The Company presently owns and operates the San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver Mine as well as a portfolio of development and exploration assets, including the Jerritt Canyon Gold project located in northeastern Nevada, U.S.A.

First Majestic is proud to offer a portion of its silver production for sale to the public. Bars, ingots, coins and medallions are available for purchase online at its Bullion Store at some of the lowest premiums available.  In Q1 2024, First Majestic will also commence bullion production from its 100%-owned and operated minting facility, First Mint, LLC, to manufacture its very own exceptional silver bullion products catering to the growing demand for physical silver.

For further information, contact [email protected], visit our website at www.firstmajestic.com or call our toll-free number 1.866.529.2807.

FIRST MAJESTIC SILVER CORP.
“signed”
Keith Neumeyer, President & CEO

The entire press release available at www.firstmajestic.com